GEORGE LAW LTD, Building and Civil Engineering

Water Treatment and Supply, Subcontract Work

Case Study - Severn Trent01 - 200

Client:
Various
Value:
£3,885,212
Contract:
Subcontract
Completion:
2006-2009

Case Study - Severn Trent02 - 200

Goscote Sewage Treatment Works - Phase 3.2, civil works for chemical dosing plant.
Interserve Project Services  ~  £240,602  ~  February 2010

Rock Tower, Bayton Common Reservoir - Pipelines and slabs.
Interserve Project Services  ~  £150,000  ~  November 2009

Case Study - Severn Trent03 - 200

Goldthorn Hill Reservoirs - Civil works for ducts and pipework.
Interserve Project Services  ~  £200,000  ~  July 2009

Newent BPS - Modifications to building, new tanks and pipework.
Interserve Project Services  ~  £170,000  ~  July 2009

 

Case Study - Severn Trent04 - 200

Monkmoor STW - Construction of new acid bund tank, bases and roadway for CHP plant and associated ducts.
May Gurney Ltd  ~  £76,000  ~  June 2009

Slade Heath and Somerford - Slade Heath - Boreholes enclosure building, Somerford - Pipeline connections.
Naston Ltd  ~  £180,000  ~  March 2009

Case Study - Severn Trent05 - 200

Goscote Sewage Works - Civil works for chemical dosing plant.
Interserve Project Services  ~  £103,226  ~  January 2009

Hayden Sewage Treatment Works - Civil works including concrete to tanks and chambers, pipework, ducts and access roads.
Interserve Project Services  ~  £500,000  ~  January 2009

Case Study - Severn Trent06 - 200

Frankley WTW Chorination Building - Modification of Chorination building including doors, walls, plastering and painting.
Interserve Project Services  ~  £64,000  ~  August 2008

C2C Flow Metering - Various sites - Flumes, ‘V’ notches, pipework, cable ducts and chambers.
Field System Designs  ~  £121,215  ~  April 2008

Case Study - Severn Trent07 - 200

Seedy Mill WTW PAC Tanks - Civil works for new PAC tanks.
Naston Ltd  ~  £96,000  ~  March 2008

Bleddfa Conduit - Refurbishment of Elan Valley Aqueduct
Naston Ltd  ~  £96,000  ~  March 2008

 

Case Study - Severn Trent08 - 200

Blakedown STW - Civil works for CROW Act scheme.
Interserve Project Services  ~  £200,000  ~  November 2007

Hampton Loade Centrifuge Building - Construction of new centrifuge building.
Naston Ltd  ~  £228,492  ~  October 2007

Case Study - Severn Trent09 - 200

Seedy Mill WTW Generator - Civil works for new generator.
Naston Ltd  ~  £70,000  ~  August 2007

Draycote WTW - Modification to existing buildings.
Interserve Project Services  ~  £20,000  ~  August 2007

 

Case Study - Severn Trent10 - 200

Campion Hills WTW - Taste and odour scheme - Structural steel process building and associated pipelines and ducts.
Interserve Project Services  ~  £300,000  ~  August 2007

Hampton Loade PAC Tanks - Civil works for three PAC tanks.
Naston Ltd  ~  £93,326  ~  June 2007

Case Study - Severn Trent11 - 200

Earls Common STW - First time sewerage works.
Morgan Est Plc  ~  £363,114  ~  March 2007

Clay Mills STW - Construction of new gasholder, installation of 300mm grit removal pipe, machine and plinths.
May Gurney  ~  £223,805  ~  March 2007

Case Study - Severn Trent12 - 200

Prestwood Pumping Station - Civil works for Fluoride dosing building.
Naston Ltd  ~  £19,735  ~  February 2007

Hampton Loade TW - Design and build civil works for tank farm and dosing pipeline and building alterations.
Naston Ltd  ~  £293,000  ~  May 2006

Case Study - Severn Trent13 - 200

Cleeve Hill Membrane - Civil works for new Cryptosporidium membrane plant.
Interserve Project Services  ~  £287,627  ~  May 2006

Childswickham Membrane - Civil works for new Cryptosporidium membrane plant.
Interserve Project Services  ~  £213,070  ~  May 2006

Case Study - Severn Trent14 - 200

Additional Flow Monitoring (13 sites) - Surveys, installation of 'V' notches, cable ducts and flooring.
Field System Designs  ~  £100,000  ~  February 2006